1. General information
2. Objectives of the intervention
Goals of the intervention
1. Creating a place for socializing for locals and tourists (1);
2. Integrating the bastion into the green belt of the city (2);
4. Battling summer temperatures through the gateway's roof and the green public market (1).
2. Integrating the bastion into the green belt of the city (2);
4. Battling summer temperatures through the gateway's roof and the green public market (1).
Quantitative targets
unknown
Monitoring indicators defined
unknown
Sustainability challenge(s) addressed
Climate change adaptation: What were the goals of the NBS?
Climate change adaptation: What activities are implemented to realize the conservation goals and targets?
Implementation activities
Building work began in March 2008, slowly but surely, occupying the open areas and dismantling the woodwork. Then came the first
surprise: a number of large trees were cut down, with the permission of the city hall, trees that ought to have become part of the “green” dimension to be created in the courtyard.The contract stipulated that the work should take twenty months from start to finish, and this was reflected in the fact that it was tackled from a number of directions at once. At the same time, details of the work in
progress and plans of the final work had to be drawn up.
The contractor hired German and later Romanian architects, but at the same time also required a design team. (4)
surprise: a number of large trees were cut down, with the permission of the city hall, trees that ought to have become part of the “green” dimension to be created in the courtyard.The contract stipulated that the work should take twenty months from start to finish, and this was reflected in the fact that it was tackled from a number of directions at once. At the same time, details of the work in
progress and plans of the final work had to be drawn up.
The contractor hired German and later Romanian architects, but at the same time also required a design team. (4)
Type of NBS project
3. NBS domains, ES and scale
4. Governance and financing
5. Innovation
Type of innovation
Please specify technological innovation
Architecturally speaking, there is a glass-lined subterranean assembly which is placed smack dab in the middle, with a shallow ramp funneling visitors downwards. Also, this is the first green roof on a historical building in Romania. (1)
Novelty level of the innovation
Please specify novelty level of the innovation
Unknown
Replicability/Transferability
Please specify Replicability/Transferability
Unknown