1. General information
2. Objectives of the intervention
Goals of the intervention
1) Solving the problem of the frequent flooding which is caused by the malfunctioning of rain drainage system;
2) Improving the comfort of living of the residents of Bydgoszcz;
3) Better protection of the roads, tram tracks, communication lines and buildings from water damage; 4) Water retention and provision of rain water for watering urban greenery [1,2].
2) Improving the comfort of living of the residents of Bydgoszcz;
3) Better protection of the roads, tram tracks, communication lines and buildings from water damage; 4) Water retention and provision of rain water for watering urban greenery [1,2].
Quantitative targets
1) Thorough renovation, reconstruction, and cleaning of over 90 km of existing canals;
2) Construction of about 14 km of new drains for rain;
3) Building several dozen retention tanks with capacities from 26 to 1800 cubic meters, including reservoirs with the possibility of reusing water for watering urban greenery;
4) Creating 22 storm water purification plants [1,2].
2) Construction of about 14 km of new drains for rain;
3) Building several dozen retention tanks with capacities from 26 to 1800 cubic meters, including reservoirs with the possibility of reusing water for watering urban greenery;
4) Creating 22 storm water purification plants [1,2].
Monitoring indicators defined
1) Effective management of rainwater in the city;
2) Less frequent flooding episodes in the city;
3) Decreased rainwater damage of the urban infrastructure [1,2]
2) Less frequent flooding episodes in the city;
3) Decreased rainwater damage of the urban infrastructure [1,2]
Sustainability challenge(s) addressed
Implementation activities
1) Thorough renovation, reconstruction, and cleaning of over 90 km of existing canals;
2) Construction of about 14 km of new drains for rain;
3) Building several dozen retention tanks with capacities from 26 to 1800 cubic meters, including reservoirs with the possibility of reusing water for watering urban greenery;
4) Creating 22 storm water purification plants [1,2].
2) Construction of about 14 km of new drains for rain;
3) Building several dozen retention tanks with capacities from 26 to 1800 cubic meters, including reservoirs with the possibility of reusing water for watering urban greenery;
4) Creating 22 storm water purification plants [1,2].
3. NBS domains, ES and scale
4. Governance and financing
5. Innovation
Type of innovation
Please specify technological innovation
Providing a well functioning sustainable rain drainage system for the first time in the city.(1)